Dear Jade,
After coordination with Jack, Please note that
1. Repair 10 or more broken motor as spare parts for the our daily operation, the new motors will just be used in the 301rooms toilets replacement.
2. The last batch motor (100 nos) has been run out and the replacement has been stopped since 21July2016; the new batch hasn’t still arrived, please advise the delivery date otherwise the replacement will be postponed a lot.
3. Every replacement completed record should be confirmed the room no., more details and exact replacement qty. need to coordinate with our technician Mr.Mo directly.
Until 20 July 2016, we confirmed that there are 91rooms toilets are fixed with new motor and new seat ring as shown as the following table and the exact room no. please refer to the attached record list. Moreover, there are 70 rooms completed by JZ and 21 rooms completed by MI.