Pursuant to this new concept of total float preallocation, the allocation of delay responsibilities between the parties can be performed in a number of ways. Prateapusanond (2003) illustrates the delay allocation by using examples of six different factual delay situations which involve the consumption of total float for noncritical path activities. In this paper, only two examples will be presented.