This simple step of inserting the new scheduling language into the construction contract documents can assure all participants’ awareness that when they consume floats, they introduce the potential that project completion time can decrease—or increase. Although the courts may endorse the concept that float time is an expiring resource permitting the individual who gets to it first to gain the benefit it provides, float ownership and allocation should always be set out deliberately and expressly in the contract documents.