The last method for allocation and management of float involves inserting float and other scheduling clauses in contract documents during the design phase. This method has been widely accepted and used in construction projects. Recent studies have also recommended that owners include the following clauses in contract documents during contract preparation: “joint ownership of float,” “no-damages-for-delay,” and “nonsequestering of float.”