The project status is as shown in Fig. 9 and Table 3; Activity C is completed as per schedule; the completion of Activity N is still uncertain and hence it is stretched to Day 7; the completion of Activity J is uncertain and hence it is stretched to Day 7; Activity H is in progress; the delay toActivities J and N delays the start of activities K and O; and the contractor continues to delay the completion of Activity N and also, concurrently, delays the completion of Activity J.