• SUBCONTRACTOR shall monitor progress on all Purchase Orders against his expediting plan and report to CONTRACTOR at weekly intervals identifying those items of equipment and materials which have a critical impact or a potentially critical impact on the WORK TIME SCHEDULE and require special attention to ensure timely WORKSITE delivery, along with an action plan to achieve it