Dear Ms. Fatollahi:
Good day.
1. According to your company’s letter (No:1394062) to our company on 28th, February, 2016, the new contract documents will be sent to us in 2 or 3 weeks. But so far we didn't receive.
2. According to your company’s planning deputy Mr. Baneshi’s email on 17th, March, 2016, the draft of final contract will send to our company by Mr. Ardalan M Esfahan. But so far we didn’t receive.
3. According to our emails on 11th, March, 2016 and 18th, March, 2016, we asked your company to send us the new contract documents and the new technical clauses from Dr. Stein. But so far we didn’t receive.
4. According to your email on 25th, March, 2016, you asked us to study the general conditions of the oldest draft. And we sent our comments to your company by emails on 29th, March, 2016 and 2nd, April, 2016. But so far we didn’t receive your replies to our comments.
5. According to your email on 29th, March, 2016, you said once your project team came back work, you would send the results to us. But we didn’t receive.
6. Accroding to your email on 6th, April, 2016, we can talk with Mr. Ashrafi or Mr. Mohamadi about these issues.
So we contacted with Mr. Mohamadi by phone call for several times on 6th & 7th April, 2016, he said he will give us your comments about the General Conditions by email. But so far we didn’t receive.
7. Also, we send you another email on 11th April, 2016 to ask for your detail comments for our every opnion . But so far we didn’t receive.
8. We are really very thankful for your invitation for us to go to Iran for negotiation. In fact my work team and I are very sincere to cooperate with your company and ready to do the project in Iran at any time.
9. we have sincerely cooperate your company long time more than 10 months, we have sent more than 20persons.times to Iran finalize the contract base on your 3 times invation, but can not complete according to the plan, and we have give your company many times discount base on trust your company, but after our study.and analysis this project's pipe is practically damaged very much, sludge and sedments conditions is bad, and when you company want to this kind of bad pipe use future advanced technology standard to meet Germany good pipe level, it will be very difficult, and our original price base on original agreed conditions is truly very low, it will be not enough to cover the cost. and we have input so much energy and money, we has already lost has not profit on this small 75km project. please be understand the truth.
However, before the new technical clauses have given to our company and the general conditions have reached an agreement by both sides, our company board still thinks that there are so many risks, and its precondition is not mature to sign the contract now, and hopes your company can well understand and prepare the whole necessary precondition technical and general conditions of contract to our company to reach the finalize conditions, also we think that any good cooperation should be under fair clauses and trust faith of both sides so that we can have a win-win situation.
Therefore, would your good company send us the new technical clauses from Dr. Stein as soon as possible and your detail replies to our every comments of the general conditions? Thank you very much.
Best regards.
Beijing Longkexing International Co., Ltd
Mr. Solo Wong