1. Cables from the Substation 1 upto the respective equipment is considered in the Package I-03 Scope of work as per the electrical Scope of work and Drawings, 2. Piping Scope upto tank is considered in the package I-03 (as per PID Scope Split between package I-01 and Package -03) Fig 2 is added for reference. 3. All the headers of petroleum products are routed upto battery limit in the pipe rack by OWNER, Contractor has considered connection from the battery limit. No pipe rack/Sleepers upto Ship loading is considered as part of scope of Package I-03