It is assumed that any soil change or any site filling done has started from verified hard layer as described in point 6,
and that the filling is done with course granular material, compacted in, depending of compaction equipment, suitable layers with
an all thru compaction level of min. 95 % Modified Proctor.
9. Access to site
It is assumed that the access to the site is suitable for heavy transportation, and that no access road / access road improvement of any kind is
needed
10. Connection points
It is assumed that connection points for rain water, water, sewage, fuel or other piping, power (for construction) and other utilities
are at the site boundary. No work outside site boundary is included.
11. Laydown area
It is assumed that a for the project sufficient laydown and working area is available, free of charge, at site or adjacent to the site
(has the same boundary line).
12. Construction obstacles
It is assumed that no limitations and restrictions of any kind are affecting the construction work (like working time restrictions, noise,traffic etc).
All the works or items mentioned here includes all material (provided, cut, fixed, supported, transported, fabricated, insulated or otherwise provided) and installation necessary
to finalise the work properly, even if not separately mentioned.
All installation shall be performed taking in account OSHA and other requirements regarding safety, like for example excavation for underground installations and temporary
supports of excavated trenches
Also all the works or items mentioned here shall include all the complementary flashings-, fastening-, sealing- and clean-up works according to installation instructions and drawings.
Steel frame inst. must also include re-tightening of bolted joints.
Structural filling-, subbase/base filling layers must be compacted to 95% modified proctor.
All amounts are theoretical amounts, calculated and given without spillage, (waste), material delivered by Wärtsilä includes normal waste (normally 2…10 %, fastening
material 15 %). All filling is calculated as ready compacted. Note! Unit prices shall be for theoretical amounts. Contractor shall automatically calculate and include
necessary spillage (extra) in the unit prices.
All reinforcement is calculated with weights according to mm-bars (Eurocode). If ASTM or other inch. reinforcement is used possible additional weight must be taking
in account by the contractor.
The concrete compression strength mentioned is for a specimen cube with dimension 150x150x150 mm.
If necessary the civil contractor shall use a layer of lean-concrete (50 mm/2"), and include it, even if it is not mentioned in the enclosed documentation.
Material that is ready-painted, and during the installation get damaged, or scratched shall be re-painted by the Contractor using paint supplied by the material manufacturer,
or by paint specified by him. The paint shall be applied in accordance with his specification.
All materials used shall be handled and fixed in accordance with the manufacturers instructions.
The quantities given are preliminary, the detailed engineering has higher priority.
Note! This Bill of Quantity list and corresponding drawings (even if not mentioned here) are complementing each other.
must be included in the price.
Certain smaller items mentioned in the drawings are not listed separately in the Bill of Quantity list.