The project status is as shown in Fig. 10 and Table 4; Activity H is completed as per schedule; Activity D has an actual start; Activity N is further delayed by 1 more day; the completion of Activity J is still uncertain, and hence it records 1 more day of delay which further delays the overall project by a day; and the delays toActivities J and N are concurrent and hence the delay to activity N does not affect the project completion or the total float values for the activities in that path. Nevertheless, the delay to Activity J delays the project completion by 1 more day and it increases the float for Activities E and I by 1 day. This newly created float is split equally between the participating parties.