Recognizing that total float is an asset for both owners and contractors, apportioning the utilization of total float needs further clarification by improving contract language. The overall purpose of this paper is to introduce the concept of float preallocation and management for CPM-based construction schedules, which avoids the pitfalls of the “first-come, first-served” utilization protocol.