We are still with the plan that we shall evacuate the solar generated power to the 33kV transmission line which runs very close (less than 1km) to our proposed project land at Tetulia through an 11/33kV substation and switching station. If Bangladesh Power Development Board (BPDB) upon their decision to get evacuated power to the nearest 33/11kV S/S, then we will have to build about 12km 33kV transmission line. We have kept provision to build it in our estimation; which is about 0.36 million US$.