The project status is as shown in Fig. 11 and Table 5;Activity I is completed as per schedule; Activity D is progressing as per schedule; Activity O has an actual start; and completion of activity J is still uncertain. Activity J is therefore stretched to Day 10. This further delays the project by 2 days and as a result increases the float for Activity E by 2 days. The participating parties share this newly created float.