The project status is as shown in Fig. 13 and Table 7; Activity E has an actual start and is progressing as per schedule; Activity K is completed on schedule; Activity O is further delayed by 4 days to its completion; and Activity O had a float of 6 days and hence this 4-day delay does not have any effect on the project completion. The delay is an owner responsible delay and hence the corresponding value is deducted from the owners ATF for Activity O.