Dell Customer Communication - ConfidentialAll,Here is the 12/3 MM of Reventon post RTS cable PPAP schedule.Attendee: IEC: Cindy, Alvin, Eric, Eva, Mark, Susan, Win.Dell: Felix, Chun-Lin, Terry, Sophie, Will, Milly, Pango1. The overall PPAP status is RED due to PPAP lack several EE test report.2. Schedule 11/29 IEC provide complete PPAP to Dell. (delay) 12/4 Dell approve all PPAP and submit ECO. 12/6 ECO completed.3. IEC EV team/ Mark need to provide report target date COB 12/3. See below table for detail action items.4. IEC missing address “single end impedance spec” at drawing and missing those report either. Dell SE/Felix had rejected all PPAP and can’t accept conditional approval. This will impact overall PPAP schedule if supplier to create report now. IEC is seeking for high-level management team’s alignment to address the risk. IEC to provide update COB 12/3. 5. G286V and DM7JC is the worst case cable for I2C and EV report. All of the other cable can leverage those report. See below for detail plan.6. Team agree to focus on Amphenol for high speed cable and Bizlink for power cable, IEC will drive both supplier to meet schedule. For those supplier’s cable which can’t get Dell approval or IEC high-level management team alignment, Dell PjM will remove them from supplier list to complete process.