重要日期: Actual time will be confirm1. Pedestal date: 12/242. pre-install material move-in: 12/193. Tool Container move-in: 1/2 14:004. 廠務會勘:1/6 10:005. Power on: 1/10 14:006. Safety check: 1/107. special gas supply: 1/178. Re-exported date: 1/10 09:00 (確認move out動線是否需要拆牆)9. CO2: 1/2210. Laser Fire: 1/2411. BRES setting and turn on: