If the current total float practice or the first-come-first-serve basis is applied to this case, the owner and the contractor will also be held responsible for the 5-day project delay; however, the result on each path will be different. On the activity path of A-B-CD, the owner will be held responsible for the 3-day delay to Activity D and the contractor will be held responsible for the 2-day delay to Activity C. On the activity path of E-F-G-H, the contractor will be held responsible for the 3-day delay to Activity H; and the owner will be held responsible for the 2-day delay to Activity G.