Tools and techniques include constraints analysis, the activity
definition model and prototyping of products or processes,
also known as first-run studies. Constraints analysis is done
by examining each activity that is scheduled to start within the
period chosen as the project lookahead window.
4
The con-
straints that prevent the activity from being a sound assign-
ment are identified and actions are taken to remove those
constraints. As shown in Table 2, the activity of designing a
slab is constrained by lack of a soils report. Acquiring the soils
report removes that constraint. Note that the addition of such
‘make ready’ tasks is one way in which the level of detail
increases as scheduled activities enter the lookahead window.
The rule governing constraints analysis is that no activity is
allowed to retain its scheduled date unless the planners are
confident that constraints can be removed in time. Following
this rule assures that problems will be surfaced earlier and that
problems that cannot be resolved in the lookahead process will
not be imposed on the production level of the project, whether
that be design, fabrication or construction.
The Activity Definition Model (ADM: Figure 4) provides the
primary categories of constraints: directives, prerequisite
work and resources. Directives provide guidance according
to which output is to be produced or assessed. Examples are
assignments, design criteria and specifications. Prerequisite
work is the substrate on which work is done or to which
work is added. Examples include materials, whether ‘raw’
or work-in-progress, information input to a calculation or
decision, etc. Resources are either labour, instruments of
labour or conditions in which labour is exercised.
Resources can bear load and have finite capacities.
Consequently, labour, tools, equipment and space are
resources, but materials and information are not.
ADM is a tool for exploding phase schedule activities into
greater detail. Explosion occurs through specification of con-
straints and through further detailing of processes.
工具和技术包括活动制约因素分析定义模型和原型设计的产品或过程,也被称为第一次运行研究。做了制约因素分析通过检查定于开始内每一项活动作为项目预测先行窗口所选期间。4Con-防止活动正在酣然的分配-的约束确定了发展和采取行动,删除那些约束。如图所示,在表 2 中,活动的设计板坯受制于缺乏的土壤的一份报告。获取土壤报告中移除该约束。请注意,这种加法'准备' 的任务是在其中的一种方法的详细程度随着计划的活动输入预测先行窗口。制约因素分析的规则就是没有活动获准保留其预定的日期,除非规划师自信可以及时删除约束。以下此规则确保问题会早些时候浮出水面,不能预测先行过程中解决的问题不会强加给该项目的生产水平是否这是设计、 制造或施工。活动定义模型 (ADM: 图 4) 提供主要类别的限制: 指令,系统必备工作和资源。指令提供指导依据输出将到生产或评估。例子是工作、 设计标准和技术规范。前提条件work is the substrate on which work is done or to whichwork is added. Examples include materials, whether ‘raw’or work-in-progress, information input to a calculation ordecision, etc. Resources are either labour, instruments oflabour or conditions in which labour is exercised.Resources can bear load and have finite capacities.Consequently, labour, tools, equipment and space areresources, but materials and information are not.ADM is a tool for exploding phase schedule activities intogreater detail. Explosion occurs through specification of con-straints and through further detailing of processes.
正在翻譯中..
![](//zhcntimg.ilovetranslation.com/pic/loading_3.gif?v=b9814dd30c1d7c59_8619)