Hi Ben,
Thanks. Can you run the model with all steel delivered to Tianjin port up to 01st November – we then get a good feel for how much is currently on site / imminently due.
Santiago – I want to prioritize the gallery section for transport. Would you please review all project requirements and direct Ben if this makes sense.
Ian – as discussed the lack of containers is hurting us. While I’m not sure on the solution we need to be squeaking loudly and placing as much pressure as we can on Maersk.
Thanks and Regards